Thursday, July 15, 2010
We have finished our first round of mowing the precinct. I have sent home the part-time employee since I now have a full crew devoted to our roads. I was a good thing as the weather has been rainy for much of the time since my last post. We have put in several culverts in the precinct, all for the county instead of home access. We put in two west of Lake Tankersley on CR1042 two solve a drainage problem in that neighborhood. We also put in a new culvert across CR1125 to replace one that was in poor condition. We have reapplied recycled asphalt to the creek bottom road on CR1680 and we have repaired a portion of CR1540 by tearing up the existing pavement, relaying the pulverized material, and topping with a good cold-mix layer. We are looking forward to our biggest job for the summer; the rebuilding of the pavement on CR1905. It should take us about two weeks to complete the job and has been waiting on a good long term forecast. Wish us luck!
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment